Metro staff recommend closing an eight-mile gap in the LA River walking and biking trail between Elysian Valley and Vernon.
The agency is recommending Modified Option 2 as the Locally Preferred Alternative (LPA) for the LA River Path Project, according to Metro's blog. The full Metro Board is scheduled to consider the recommendation on Dec. 3.
The project carries an estimated price tag of $872 million. It has $433 million in funding from Measure M. Securing the remaining money depends in part on completing environmental studies, Metro said.
What the path would look like
Modified Option 2 would build the trail mostly on top of the riverbank or cut into its side. Elevated structures would bridge railroad tracks and cross the river where needed.
Metro staff said the approach is more practical and cost-effective than alternatives. A bottom-of-channel path was considered during earlier planning but dropped. Staff said a river-bottom trail would face multi-day closures during rain, require longer and potentially steeper ramps in some locations, and sit at least 25 feet below the top of the channel, reducing visibility and perceived safety.
The recommended route includes three new river crossings and 10 new access points. Seven access points would sit on the east bank and three on the west bank. Two more at 7th Street and the intersection of Bandini and Soto could be added if future funding is found.
Two segments would come first
Staff are recommending that two initial segments be built at the same time. The northern segment would run between Riverside Drive and Broadway/Spring Street. The southern segment would stretch between Sixth Street and Atlantic Boulevard.
Together, those segments would close 5.5 miles of the eight-mile gap. Combined with existing and planned bike lanes near the river, the two segments would provide a fully protected path for cyclists across the entire gap in the interim. Funding for the remaining 2.5-mile in-channel stretch has not yet been secured, Metro said.
The gap runs through downtown Los Angeles, Boyle Heights, Vernon and Maywood. The broader LA River trail network stretches 51 miles, from the San Fernando Valley to near where the river meets the Pacific Ocean in Long Beach.
What comes next
Metro's Planning and Programming Committee on Wednesday, Nov. 18 and Executive Management Committee on Thursday, Nov. 19 considered the LPA before the scheduled full board review.
Big questions remain. Before final design and environmental clearance under the California Environmental Quality Act (CEQA) can proceed, agencies must commit to owning and maintaining the path. Metro owns less than 1% of the land the trail would cross and said it will not pay to operate or maintain the path once it opens.
Metro's Board has directed the Los Angeles County Flood Control District to lead a governance study evaluating how the project could be delivered and managed long-term. Metro said it will fund the study and is working with Los Angeles County on its scope, schedule and budget.
Members of the public can attend the board meeting in person or watch online through Metro's board meeting website.