The Vincent Thomas Bridge shuts down Saturday for at least 16 months while crews replace its deteriorating deck in a $750 million project.
The closure begins at 12:01 a.m. Nov. 7, according to KTLA. The bridge, part of State Route 47, carries about 53,000 vehicles a day between San Pedro and Terminal Island, with connections to Long Beach. That traffic will be funneled onto alternate routes until at least early March 2028.
Caltrans District 7 spokesperson Nathan Bass told KTLA the 63-year-old bridge has been worn down by decades of heavy use. "The bridge has taken on increasingly heavy traffic loading throughout its long service life and it's also been deteriorated by the marine environment around it," Bass said.
Bass said the bridge structure itself remains safe. The deck, though, has degraded under the weight of roughly 4,600 heavy trucks crossing it each day, the Long Beach Post reported. A 2021 Caltrans inspection found the deck's condition had dropped from "fair" to "poor," according to the Post.
What drivers should know
Caltrans is directing San Pedro drivers to the 110 Freeway to Harry Bridges Boulevard, then to the 47 Freeway at Henry Ford Boulevard or the 710 Freeway. Traffic control officers will be posted at 18 intersections to manage flow, KTLA reported. Commercial truckers who cut through residential neighborhoods risk citations.
Caltrans resurfaced and restriped detour roads ahead of the closure. The agency also installed traffic cameras and temporary signals along the routes and worked with online mapping services including Waze to flag detours, according to the Los Angeles Business Journal.
Caltrans also notified Google Maps and Apple Maps about the closure, LAmag reported.
The detours could double some commute times. San Pedro resident Tate Allen, who drives to his downtown Long Beach office three days a week, estimated his 15-minute trip will stretch to 30-45 minutes, the Post reported. Allen and his neighbors have started calling the closure "Harborgeddon."
Businesses brace for impact
Stephanie Crawford, who has owned Creative Pet Supply in San Pedro for 26 years, told the Post that Long Beach customers have been asking how they'll reach her store. "We'll still be open, if you can get to us," she said.
Liz Schindler Johnson, executive director of the Grand Vision Foundation, said 10-15% of the audience at the historic Warner Grand Theatre in downtown San Pedro comes from Long Beach. Two of her eight employees commute over the bridge. "We don't want to go back to remote work if we can help it," Schindler Johnson told the Post.
Why a full shutdown
Caltrans chose a complete closure over partial options. Night-only closures would have stretched the project to 48 months. A mix of weekend and overnight closures keeping one lane open would have taken 25 to 32 months, according to the Post. Caltrans also said temporary closures over several years would cost more, ABC7 reported.
Along with the deck, the project will replace the center median, railings and fencing, and install new seismic sensors. California Engineering Contractors and Stockholm-based Skanska are the primary contractors, according to the Business Journal.
Los Angeles City Councilmember Tim McOsker, who represents District 15 including San Pedro and Wilmington, pushed for road improvements along detour routes before the closure. In Wilmington, those efforts included slurry sealing along Alameda Street and Harry Bridges Boulevard, with concrete repairs at some locations, according to spokesperson Sophie Gilchrist. McOsker also asked the Los Angeles Department of Transportation to monitor Anaheim Street traffic and identify fixes if problems arise, Gilchrist said.
Caltrans is also providing air filters to homes near the bridge to address pollution from idling trucks. About 7,000 homes received notices about the program, ABC7 reported.
The target completion is early March 2028, roughly four months before Olympic sailing events are scheduled in the area, according to the Business Journal.