The Pacific Palisades Branch Library is the only stand-alone civic building destroyed in the January 2025 Palisades Fire that still lacks an architect. The nonprofit group that supports it wants to know why.
Cameron Pfizenmaier, president of the Friends of the Palisades Library, sent a formal letter Wednesday, Sept. 9, to Los Angeles City Engineer Crystal Lee demanding an explanation for the 195-day gap since architectural proposals were due. No contract has been awarded or publicly identified, according to the Palisadian-Post, which first reported the letter.
The Bureau of Engineering issued its request for proposals on Dec. 22, 2025, with submissions due Jan. 26. That RFP was restricted to firms already on the bureau's pre-qualified consultant list, a process meant to speed things up. Six months later, nothing has happened.
"The community is entitled to understand why, more than six months after proposals were due, that process has not produced a publicly identified architect under contract," Pfizenmaier wrote in the letter.
Other fire-damaged facilities have moved faster. The Palisades Recreation Center had a design partner engaged within 93 days of the fire. The Los Angeles Unified School District obtained board authorization for a $604 million three-campus reconstruction program within 147 days. The library's RFP did not go out until day 336.
The letter also points to Mayor Karen Bass's own commitments. At an April 17, 2025, press conference at the library site, Bass said the city had prioritized debris removal on city-owned properties "to expedite the timeline to get them rebuilt and returned to this community." Her Emergency Executive Order No. 5, issued March 21, 2025, directed the Bureau of Engineering to coordinate with the library system on climate- and fire-resilient rebuilds.
Money does not appear to be the bottleneck. California approved $22.496 million in federal advance funding for the library's reconstruction in July 2026 through Assembly Bill 100, the Palisadian-Post reported. The city's fiscal year 2026–2027 budget added a dedicated architect position for the project. Yet a separate $1.8 million transfer that City Administrative Officer Matthew W. Szabo recommended on May 5 to launch the initial design phase still awaited City Council approval as of July.
City documents indicate that even if that transfer were funded immediately, the design phase would not wrap up until at least December 2027. That timeline puts the project behind its original four- to five-year reconstruction goal.
A temporary library opened in two portable buildings in the parking lot of the original site in February 2026.
The Friends group, founded in 1961, is asking the city to explain the delay, set a target date for public input and architect selection, and release a detailed timeline with milestones and responsible departments.
Copies of the letter went to City Librarian John Szabo, Councilwoman Traci Park, Marian Ensley of the Mayor's recovery office, Pacific Palisades Community Council President Allison Holdorff Polhill, and Cynthia Stein, a senior counselor for recovery in Governor Gavin Newsom's office. No public response from the city or the Bureau of Engineering had appeared as of Sept. 10.